Power line not needed, judges say

Fri. August 22, 2008; Posted: 05:44 AM
Stocks RSS
Aug 22, 2008 (The Pittsburgh Tribune-Review - McClatchy-Tribune News Service via COMTEX) -- AYE | Quote | Chart | News | PowerRating -- Aug. 22--Allegheny Energy Inc.'s controversial $1.2 billion, high-voltage power transmission line project isn't needed, two state Public Utility Commission administrative law judges said Thursday.

After reviewing more than 2,000 pages of testimony, listening to testimony at 12 public hearings and making three site visits, Judges Mark A. Hoyer and Michael A. Nemec in a 364-page document said Allegheny Energy, through its transmission line subsidiary TrAILCo, had "failed to carry the burden of truth" for the 240-mile project.

Allegheny Energy officials said the decision is only a recommendation and that TrAILCo will continue to pursue the matter with the full PUC before the commission schedules a final vote.

"We are extremely disappointed in this administrative recommendation, which runs counter to the evidence presented," said Paul J. Evanson, chairman, president and chief executive officer of Allegheny Energy. "We intend to vigorously pursue construction of this line with the commission ... ."

The state Office of Consumer Advocate and the PUC's Office of Trial Staff had publicly opposed the Trans-Allegheny line.

"We believe that the 500-kilovolt line through Washington and Greene counties isn't necessary," said Irwin "Sonny" Popowsky, the state's consumer advocate. "Our expert witness believes that construction of smaller transmission lines on existing company rights of way would be less costly and cause less environmental impact."

Office of Trial Staff analyst Gary Yocca testified he doesn't believe Allegheny Energy has satisfied all applicable statutes and regulations regarding the new transmission line.

Allegheny Energy and PJM Interconnection LLC, the entity which oversees the power grid and includes Pennsylvania, has said the power line was needed to move inexpensive, coal-fired electricity from this area to the East Coast.

Allegheny Energy argued that the Pennsylvania portion of the project was needed due to the rapid increase in power needs for the area, particularly in Washington County.

"PJM Interconnection ... determined that this line was necessary for the reliable supply of electricity to homes and businesses throughout the Mid-Atlantic region and mandated its construction," Allegheny Energy's Evanson said.

The judges broke the entire Trans-Allegheny transmission line into two segments. The so-called Prexy portion would include a 500,000-volt line that runs north from the West Virginia border through Greene County to a substation near Eighty Four in Washington County. Three new 138,000-volt lines are part of the Pennsylvania portion of the project, with all transmission lines combined crossing some 53 miles of the state. The project was to be completed in 2011.

"The proposed Prexy segment project is a grandiose answer to a minor or even nonexistent problem," the judges wrote.

The major portion of the project would be the 500,000-volt line, running from the West Virginia border, through West Virginia, to Loudoun County, Va., about 35 miles west of Washington, D.C.

Allegheny Energy's portion of the project would stop at the Virginia line and cost the Greensburg-based energy company about $850 million. Dominion Virginia Power would construct the Virginia portion of the transmission line.

"Granting approval of the 502 Junction (at the West Virginia border) to Loudoun segment at this juncture rewards a lack of foresight and proper maintenance, and has policy implications for the location of future generation that should be carefully considered before any further action is taken," the judges wrote.

The judges further chided Allegheny Energy/TrAILCo for not considering nontransmission alternatives, and questioned the modeling used to support the "alleged" need for the 502 Junction to Loudoun segment. The judges didn't specify in their recommendations what alternatives may be available.

The judges, who made their recommendations to the PUC commissioners, rejected TrAILCo's filing and evidence concerning route selection and siting for the transmission lines.

"We conclude that TrAILCo has not complied with this commission's requirements for route selection and siting," the judges said.

People impacted by the transmission line's proposed route and public officials -- a majority came out strongly against the project -- were pleased with the judges' recommendations.

"I am pleasantly surprised with the decision," said Pam Snyder, chairman of the Greene County commissioners and a property owner whose farm in Jefferson would have been impacted by the line.

"I had hoped that the PUC would have listened to the people, but I also knew they had to listen to both sides. It's just such a good feeling."

The Trans-Allegheny transmission line had run into public outcry almost from the day the project was announced more than two years ago. A citizens group called "Stop the Towers" gathered petition signatures, ran its own Web site and protested at the public hearings.

Parties in the case have an opportunity to file exceptions to the decision and then replies to those exceptions, said PUC spokeswoman Jennifer Kocher. Exceptions are due Sept. 10 and replies are due Sept. 22.

A vote by the commission will take place sometime after that, Kocher said.

To see more of The Pittsburgh Tribune-Review or to subscribe to the newspaper, go to http://www.pittsburghlive.com/x/pittsburghtrib/. Copyright (c) 2008, The Pittsburgh Tribune-Review Distributed by McClatchy-Tribune Information Services. For reprints, email tmsreprints@permissionsgroup.com, call 800-374-7985 or 847-635-6550, send a fax to 847-635-6968, or write to The Permissions Group Inc., 1247 Milwaukee Ave., Suite 303, Glenview, IL 60025, USA.

For full details on Allegheny Energy Inc (AYE) click here. Allegheny Energy Inc (AYE) has Short Term PowerRatings of 5. Details on Allegheny Energy Inc (AYE) Short Term PowerRatings is available at This Link.

    


More News:   Market Updates | Stock Alerts | All Trading News | Stock Index

Email
Print
Archives
Feedback
Email Article Link
Close X
Recipients email address
Your name
Your email
Add a note (optional)




Stocks RSS





Related News [AYE]
PREMIER SPONSORED LINKS
TRADE CENTER
 
The TradingMarkets Directory
RELATED SITES
Nothing but forex
Please call 1-213-955-5858 ext. 1

About TradingMarkets | Contact | Advertise | Careers | Link to Us | Site Map | Help | Terms & Conditions | Privacy Policy | Return Policy | Testimonials | Feedback

Disclaimer:

The Connors Group, Inc. ("Company") is not an investment advisory service, nor a registered investment advisor or broker-dealer and does not purport to tell or suggest which securities or currencies customers should buy or sell for themselves. The analysts and employees or affiliates of Company may hold positions in the stocks, currencies or industries discussed here. You understand and acknowledge that there is a very high degree of risk involved in trading securities and/or currencies. The Company, the authors, the publisher, and all affiliates of Company assume no responsibility or liability for your trading and investment results. Factual statements on the Company's website, or in its publications, are made as of the date stated and are subject to change without notice.

It should not be assumed that the methods, techniques, or indicators presented in these products will be profitable or that they will not result in losses. Past results of any individual trader or trading system published by Company are not indicative of future returns by that trader or system, and are not indicative of future returns which be realized by you. In addition, the indicators, strategies, columns, articles and all other features of Company's products (collectively, the "Information") are provided for informational and educational purposes only and should not be construed as investment advice. Examples presented on Company's website are for educational purposes only. Such set-ups are not solicitations of any order to buy or sell. Accordingly, you should not rely solely on the Information in making any investment. Rather, you should use the Information only as a starting point for doing additional independent research in order to allow you to form your own opinion regarding investments. You should always check with your licensed financial advisor and tax advisor to determine the suitability of any investment.

HYPOTHETICAL OR SIMULATED PERFORMANCE RESULTS HAVE CERTAIN INHERENT LIMITATIONS. UNLIKE AN ACTUAL PERFORMANCE RECORD, SIMULATED RESULTS DO NOT REPRESENT ACTUAL TRADING AND MAY NOT BE IMPACTED BY BROKERAGE AND OTHER SLIPPAGE FEES. ALSO, SINCE THE TRADES HAVE NOT ACTUALLY BEEN EXECUTED, THE RESULTS MAY HAVE UNDER- OR OVER-COMPENSATED FOR THE IMPACT, IF ANY, OF CERTAIN MARKET FACTORS, SUCH AS LACK OF LIQUIDITY. SIMULATED TRADING PROGRAMS IN GENERAL ARE ALSO SUBJECT TO THE FACT THAT THEY ARE DESIGNED WITH THE BENEFIT OF HINDSIGHT. NO REPRESENTATION IS BEING MADE THAT ANY ACCOUNT WILL OR IS LIKELY TO ACHIEVE PROFITS OR LOSSES SIMILAR TO THOSE SHOWN.

The Connors Group, Inc.
15260 Ventura Blvd., Ste. 2200
Sherman Oaks, CA 91403

© Copyright 2009 The Connors Group, Inc.


All analyst commentary provided on TradingMarkets.com is provided for educational purposes only. The analysts and employees or affiliates of TradingMarkets.com may hold positions in the stocks or industries discussed here. This information is NOT a recommendation or solicitation to buy or sell any securities. Your use of this and all information contained on TradingMarkets.com is governed by the Terms and Conditions of Use. Please click the link to view those terms. Follow this link to read our Editorial Policy.

© 2009 The Connors Group, Inc.